SHARE
COPY LINK

STORM

Storms abate in western Sweden

Last night's near hurricane force winds off the west coast of Sweden showed signs of letting up this morning.

Storms abate in western Sweden

The storm was accompanied by heavy rain, according to rescue services coordinator Birger Knutsson of the Göteborg Sjöräddningscentralen (‘Maritime Rescue Centre’).

“The wind has hardly affected commercial shipping, and pleasure boaters seem to have stayed ashore while the storm was at its height,” said Knutsson to the TT news agency.

“About ten vessels were anchored under Skagen waiting for calmer weather.”

Early this morning, weather stations along the west coast down as far as Skåne reported winds of 20-23 metres per second, with gusts of up to 23–31 mps.

Many trees and branches were blown down in the storm, damaging power lines and causing major electricity supply disruptions in neighbouring Halland, Bohuslän and Värmland, according to a Fortum press release.

Some 3,000 homes were still without electricity at around eight o’clock this morning. Kalmar saw the biggest disruptions, with 1,000 customers affected, according to an Eon report.

WIND

Denmark approves plans to build North Sea ‘energy island’

Denmark has moved forward with plans for an artificial island in the North Sea that could generate wind power for at least three million households, a government spokesman said on Friday.

Denmark approves plans to build North Sea 'energy island'
File photo: Henning Bagger/Ritzau Scanpix

Work is due to begin by 2026, he added. 

The Danish parliament adopted in June a political environmental framework aimed at reducing the country's CO2 emissions by 70 percent by 2030, which included plans for the world's first “energy hubs” on the island of Bornholm in the Baltic Sea and in the North Sea.

On Thursday, parliament went further by approving a plan to place the North Sea hub on an artificial island, with a wind power farm that will initially supply three gigawatts (GW) of electricity.

That could later be scaled up to 10 GW — enough for 10 million households — according to the Danish Ministry of Climate, Energy and Utilities.

The island is to be majority owned by the Danish government in partnership with private companies.

Its final size is yet to be decided but it is expected to cover between 120,000 to 460,000 square meters (about 1.3 to 5 million square feet), ministry spokesperson Emil Lee Madsen told AFP.

The total number of wind turbines has not been finalised either, but estimates range between 200 and 600 units at “a previously unseen scale,” with the tip of the blades reaching as high as 260 meters (850 feet) above the sea.

The project's next steps include environmental impact assessments and talks with potential investors, so construction is still some years off.

“At this point it seems like initial construction will actually begin around 2026, and hopefully it will be finished sometime between 2030 and 2033,” Lee Madsen said, noting that some delays were probable so closer to 2033 was more realistic.

At full capacity, the island would provide more wind power than Denmark needs for its population of 5.8 million.

Other countries could then plug into the hub to “increase the efficiency of the electricity production from the wind farms by distributing it across the European power grid,” the ministry said.

READ ALSO: Denmark proposes giant 1.3GW wind to jet fuel plant

SHOW COMMENTS